Week 3 was a slow week due to the Memorial Day weekend but we still got  some things done.  

The stone for the fireplace arrived on Tuesday - we were told not to expect it till mid week NEXT week.

Backer Board was installed for the tile bathrooms by Frank Carbonell, owner of Off The Wall Backsplashes.  


Then Frank started on tiling the floors.  He is scheduled to be finished by the 8th with the floors, shower, and rocking the fireplace.





Once he finishes James Hussey of Hussey Flooring will come in and lay the rest of the floors and the carpet in the bedrooms.

There were a couple of unexciting things like a couple of lights installed in the closets and a CO2 detector installed.

Bathroom vanities arrived and waiting for installation.

So on Week 4, we should see:

Tile Completed

Fireplace Completed

Floors Finished

Windows Installed

Cabinets will arrive

So week 4 and 5 should show the MOST change.